CYCLONE GABRIELLE UPDATES: View our traffic map for the latest available information on road closures and delays(external link) and find out about closures to driver licensing sites

SCAM ALERTS: Report a phishing scam or learn about the latest phishing emails

TRAFFIC UPDATES: Several roads have been impacted by recent weather events. We’ll provide updates on our Journey Planner website as information becomes available. View our traffic map for road closures and delays(external link)

SCAM ALERTS: Report a phishing scam or learn about the latest phishing emails

CONTACT CENTRE WAIT TIMES: Our Contact Centre is currently experiencing significant wait times. View frequently asked questions

ONLINE TRANSACTIONS: We are experiencing issues with credit and debit card transactions on our website. We are working with the payment provider to resolve this as soon as we can. 

CONTACT CENTRE WAIT TIMES: Our Contact Centre is currently experiencing significant wait times. View frequently asked questions

REGO AND RUC LABEL ERROR: There was a postage error with labels purchased on the 15 August 2022. Find out more

ROAD USER CHARGES (RUC) DISCOUNT: Find out more about the temporary RUC reduction scheme

ONLINE SERVICES: We are currently experiencing issues with all our online services at the moment. We are working to resolve the services as soon as possible. We apologise for any inconvenience caused.

COVID-19 SERVICES UPDATE: Information on Waka Kotahi services, extensions and more

ONLINE SERVICES: We currently have an issue with receiving some payments and are working to resolve this issue as quickly as possible. We apologise for any inconvenience.

EASTER WEEKEND – PLAN AHEAD: Heading away for the long weekend? Check our holiday journeys tool(external link)

SCAM ALERTS: Refund email and Vehicle licence (rego) renewal phishing emails

CONTACT CENTRE PHONE LINES: Our Contact Centre phone lines are currently unavailable. View frequently asked questions

NZTA reopens southbound lanes on Newmarket Viaduct early

|

The NZ Transport Agency has re-opened all southbound lanes on Auckland's Southern Motorway (State Highway 1) - two hours early than planned after a successful overnight operation to connect or stitch together the new southbound and northbound viaducts across Newmarket.

Three of the four southbound lanes on the viaduct were closed at 6pm last night (Saturday, 3 September) and were due to re-open at midday today. The NZTA  lifted the closures at ten o'clock this morning.

The NZTA's State Highways Manager for Auckland and Northland, Tommy Parker, thanked drivers for their support during the closure.

"We were able to complete the concrete stitch ahead of schedule and the cooperation of drivers helped to make this possible. Most people planned their journeys to allow extra time for their travel or avoided the viaduct altogether. Once the early evening rush had passed, traffic flowed smoothly."

The lanes were closed so that the NZTA and its partners on the Newmarket Viaduct replacement project could fill the 1.1 metre-wide gap between the new viaducts with concrete to make one complete structure.

Thirty-two truckloads of concrete and 40 contractors working in teams of six "stitched" the 690 metre-long gap. The pour was completed ahead of schedule at 11.45pm and then the concrete was allowed to set.

Mr Parker praised the contractors who worked through the night.

"It was a great display of team work, and their commitment to get the job done has helped minimise any disruption to drivers," Mr Parker says.

Now that the Stitch has been completed, work will continue to prepare the new northbound half of the viaduct for traffic. Switching traffic from the existing northbound viaduct to its improved and stronger replacement will be made over Auckland Anniversary weekend, 28-30 January.  This will involve closing all three northbound lanes of the motorway at Newmarket for 36 hours. Diversions will be in place and clearly marked.

"It's a critical few weeks for the Newmarket project - one of our most important undertakings as part of the NZTA's Motorways Summer Season programme to improve the flow of traffic safely through central Auckland" says Mr Parker.