CONTACT CENTRE WAIT TIMES: Our Contact Centre is currently experiencing significant wait times. View frequently asked questions

SCAM ALERTS: Report a phishing scam or learn about the latest phishing emails

ONLINE TRANSACTIONS: We are experiencing issues with credit and debit card transactions on our website. We are working with the payment provider to resolve this as soon as we can. 

CONTACT CENTRE WAIT TIMES: Our Contact Centre is currently experiencing significant wait times. View frequently asked questions

REGO AND RUC LABEL ERROR: There was a postage error with labels purchased on the 15 August 2022. Find out more

CONTACT CENTRE WAIT TIMES: Our Contact Centre is currently experiencing significant wait times. View frequently asked questions

ROAD USER CHARGES (RUC) DISCOUNT: Find out more about the temporary RUC reduction scheme

ONLINE SERVICES: We are currently experiencing issues with all our online services at the moment. We are working to resolve the services as soon as possible. We apologise for any inconvenience caused.

COVID-19 SERVICES UPDATE: Information on Waka Kotahi services, extensions and more

ONLINE SERVICES: We currently have an issue with receiving some payments and are working to resolve this issue as quickly as possible. We apologise for any inconvenience.

EASTER WEEKEND – PLAN AHEAD: Heading away for the long weekend? Check our holiday journeys tool(external link)

SCAM ALERTS: Refund email and Vehicle licence (rego) renewal phishing emails

CONTACT CENTRE WAIT TIMES: Our Contact Centre is currently experiencing significant wait times. View frequently asked questions

CONTACT CENTRE PHONE LINES: Our Contact Centre phone lines are currently unavailable. View frequently asked questions

Here we’ll keep you updated on timeframes, investment signals and key milestones to help you develop your funding proposals seeking inclusion in the 2024-27 NLTP.

Investment signals

Investment signals for the 2024-27 NLTP, released in October 2022

Indicative timeline

This indicative timeline outlines the key dates, milestones and deadlines for the development of the 2024-27 NLTP.

2024-27 NLTP indicative timeline [PDF, 107 KB]

Frequently asked questions - indicative timeline for developing NLTP 2024-27 [PDF, 309 KB]

This timeline remains indicative as there may be times when NLTP’s development is delayed, for example, due to late release of the Government Policy Statement on land transport (GPS), and we may adjust the timeframes for RLTPs as a result.

Indicative dates for the 2024-27 NLTP development

October 2022 onwards

Waka Kotahi issues first investment signals

December 2022      

Regional Land Transport Plan (RLTP) problem statements and ten-year priorities confirmed by Regional Transport Committees (RTCs)

June 2023

Waka Kotahi delivers final State Highway Investment Proposal

August 2023

Transport Investment Online (TIO) is updated and ready for use

Waka Kotahi & approved organisations submit initial bids for continuous programmes

September 2023

Waka Kotahi & approved organisations submit initial bids for improvement activities (incl. LCLR)

December 2023

Waka Kotahi & approved organisations submit final continuous programmes & improvement activities (incl. LCLR)

February 2024

Waka Kotahi releases indicative allocations

April 2024

RLTPs approved by regional councils and submitted to Waka Kotahi

June 2024

NLTP is adopted

July 2024

NLTP and RLTPs are published

Lessons learned

We recently completed a lessons learned exercise looking at how we can improve our processes and make things easier for the development of the next NLTP.

Report on lessons learned for the 2021-24 NLTP [PDF, 1.5 MB]