Tirohanga whānui kaupapa – project introduction

Waka Kotahi is working to keep people moving on the Far North roading network, now and in the future. We’re aiming to create resilient roads which will better withstand the impact of weather events and environmental factors.

Construction programme for slip repairs confirmed: SH1 Mangamuka Gorge to reopen May 2024

A programme of works to repair the 15 significant slips along SH1 Mangamuka Gorge has been confirmed, following $100M of funding announced at the end of 2022 and a construction contract awarded in late-February 2023.

The road is scheduled to open and be fully operational by May 2024. Acknowledging the importance of the route to connect whānau, road users, and communities on either side of the gorge, we are actively investigating opportunities to provide limited access to light vehicles over the Christmas period.

Enabling works began in late-February to ensure the road is safe and stable enough to accommodate the large machinery needed to carry out slip repairs, while we finalised detailed designs.

We will continue to keep Far North communities updated as the work progresses and will collaborate with hapū, iwi, community representatives, members of the freight industry about long-term resilience thinking.

To find out more about the Mangamuka Gorge and the work we’ll be carrying out, more information is available below.  

Information flyer

Project information boards

Watch the latest video


  • Estimated project dates

    May 2024
  • Project type

    Road maintenance
  • Project status

    Construction

Subscribe to updates

What does subscribing mean? Please read our Privacy statement

 

Te Pūtake – purpose

The Far North State Highway Resilience Programme will provide a reliable, resilient, and safe State Highway network to connect the Far North District with the rest of Te Tai Tokerau Northland and Aotearoa New Zealand.

The Programme comprises long-term resilience planning with considerations for State Highway 1 (SH1), State Highway 10 (SH10) and local roads following the SH1 Mangamuka Gorge closure in August 2022.

It also includes emergency work in the Mangamuka Gorge to prevent further damage and on SH10 to ensure that it is working efficiently to accommodate the additional vehicles with SH1 closed.

Te Kaupapa – background

A reliable and resilient roading network is essential to ensure that whānau, friends, businesses and communities stay connected. This is especially important for communities in the Far North where in many places, people live rurally and rely on state highways to get where they’re going safely.

SH1 near Mangamuka Gorge closed in August 2022 for the second time in two years due to significant slip damage caused by severe weather.

We have begun repair work on the 15 significant slips which were a result of the August 2022 event. As part of the repair, we’ll be making the ground less susceptible to slips by improving the drainage through the gorge, so it’s more suitably equipped to handle the increase in severity and frequency of weather events.

The road will reopen and be fully operational by May-2024. We are actively investigating options to provide restricted access for light vehicles over the summer period and will share more information on what’s possible closer to the time.

With climate change causing more frequent and severe weather events across the country, as well as the sensitive geology through the Maungataniwha Ranges, the Mangamuka Gorge is facing a long-term resilience issue.

Waka Kotahi is working alongside key partners including hapū, local stakeholders and key experts to review the roles of SH1, SH10 and local roads (including Broadwood/Herekino) to provide a resilient network.

Discussions with these partners and key stakeholders will help to confirm the approach to the long-term resilience solutions needed, including examining options, assessing costs and scoping risks.

We are taking a collaborative approach, utilising the extensive knowledge that Far North community representatives and experts hold to help determine our next steps.

This technical work and feedback from our partners will feed into a business case with a recommended way forward, to be considered by the Waka Kotahi Board in mid-2023.

Project map

He aha ngā kaupapa matua? – what’s included?

Protect - completed

  • Funding for immediate recovery work to protect the Mangamuka Gorge from further damage and improve efficiency on SH10.
  • This includes adding bunds around current slips to divert rainfall, sealing major cracks and stabilising work within the gorge.
  • Slip repairs on SH10 near Waitaruke to reopen the state highway to two lanes as well as bridge strengthening work at Waitangi River Bridge and Parapara Bridge to safely remove speed and weight restrictions.

Restore

  • $100M funding has been allocated for full repairs of 15 major slips within the gorge.
  • As part of the repair, we’ll be making the ground less susceptible to slips by improving the drainage through the gorge, so it’s more suitably equipped to handle the increase in severity and frequency of weather events.
  • SH1 Mangamuka Gorge is expected to reopen and be fully operational in May 2024.
  • We are actively investigating opportunities to provide limited access to light vehicles over the Christmas period to connect whānau, road users, and communities on either side of the gorge. We will share more information closer to the time as work progresses.

Build back better

  • Investigations for longer-term solutions to ensure the Far North roading network can better withstand future weather events.
  • This includes a business case for options on how we can best improve resilience on the Far North roading network and where any investment should be focused. This business case is being created in collaboration with iwi and hapū, technical experts and local key stakeholders.
  • We’ll also consider this from a national climate change perspective, and how we can respond better to these types of events across the motu.

E haere ake nei – looking ahead

View/download larger image [PNG, 94 KB]

When planning the long-term solution for a resilient roading network in the Far North, it’s important that we get the decision-making process right. There are many factors to balance including, safety, climate change, affordability, as well as economic and community impacts. Because this is such a complex piece of work, it may take some time for us to determine what the next steps are. Once they are clear, we will share an update with the community.

Detour route map

The official detour route is via SH10 and may add up to 40 minutes to your journey. This route is safe for all vehicles, including heavy and freight vehicles.

The Twin Coast Discovery Route is also open and provides a scenic alternative for light vehicles and campervans.

Whakapā mai – contact us

If you have any questions, don’t hesitate to contact the project team at northlandproject@nzta.govt.nz

Frequently asked questions

  • When will the road open?

    SH1 Mangamuka Gorge is planned to reopen and be fully operational by May 2024.

    We are actively investigating opportunities to provide limited access to light vehicles over the Christmas period to connect whānau, road users, and communities on either side of the gorge. We will share more information closer to the time as work progresses.

    Close
  • Why will it take so long to open the road?

    The weather event in August 2022 resulted in 15 significant slips with almost all requiring a complex engineering solution. Each slip will take on average 5-6 months each to repair. 

    This means there will be multiple work sites operating in parallel in an already constrained environment.

    The movement of people, large machinery and materials around site needs to be carefully planned. We are working as quickly as possible while also looking out for the safety of our people and maintaining the integrity of the road. 

    We accelerated pre-construction work including securing the required funding, designing the complex repair plans, and mobilising the people and equipment needed to carry out the work.

    Close
  • Will rain affect work on site?

    In heavy rain or during severe weather events, our people will stop work as it is not safe to work in very wet conditions, especially in a constrained and unstable environment like the gorge.

    We continually monitor and assess weather conditions to ensure the safety of our people and to maintain the integrity of the road to ensure no further damage occurs.

    Close
  • Why don’t you build a tunnel or a new state highway?

    Both options would require significant investment.

    On average, the state highway through Mangamuka Gorge carries only about 1300 vehicles per day, as compared to somewhere like the Brynderwyn Hills, which carries around 10,000. This means the business case for such a large investment would not meet the criteria for Waka Kotahi funding.

    We are investigating other longer-term solutions to ensure the Far North roading network can better withstand future weather events and improve resilience of the roading network in the region.

    We understand that SH1 through the area is a social and economic lifeline, and we are committed to ensuring it is resilient for the Far North Communities who rely on it.