Project introduction

We are replacing the 2-lane Pepe Stream Bridge on SH25 in Tairua with a new two-lane bridge. Work starts later in 2026 with traffic on the new bridge by December 2027.

  • Estimated project dates

    Sept 2026–Dec 2027
  • Project type

    Bridge replacement
  • Project status

    Consenting

Project updates

Coromandel update December 2025
Newsletter,
Coromandel update 18 November 2025
Newsletter,
Coromandel Update 3 November 2025
Newsletter,
Coromandel update 20 October 2025
Newsletter,
Coromandel Update 10 October 2025
Newsletter,
Coromandel Update September 2025
Newsletter,

Subscribe to updates

What does subscribing mean? Please read our Privacy statement

 

Project status

Funding was approved in mid-2024 and the replacement bridge project is moving through the procurement phase.

Fulton Hogan is the successful contractor and will build the new 2-lane bridge, working with engineering consultancy WSP to support the design and preparation of resource consent applications.

Artist’s impression of the new 2-lane bridge

  • Timeline

    Stage 1:​

    • Consent conditions application by March 2026​
    • Detail design by June 2026​
    • Have consents granted by August 2026​

    Stage 2:​

    • Start construction by September 2026​
    • Complete construction by December 2027​
    Close

Background

A business case was developed by NZTA in 2022 to consider and test the options for a bridge replacement. Engagement with iwi and stakeholders led to identifying the preferred option – a two-lane bridge with an attached shared walking and cycling path. This was known as option one (as presented during our community engagement session).

Option one(external link)

The bridge crosses a narrow tidal estuary on SH 25 south of Tairua’s commercial centre. The narrow three-span bridge was constructed in 1942 and has reached the end of its design life.