About the programme

Each summer, NZTA carries out a road renewal programme to keep Northland and North Auckland’s state highways safe and accessible, in order to support economic growth and productivity. Our teams maintain and manage the state highways from north of Woodhill and Warkworth all the way to Te Reinga Wairua (Cape Reinga).

We prioritise road safety, reducing disruption and minimising future costs by targeting areas with the greatest needs, focusing on the high-risk areas and those with high traffic volumes. Most maintenance work happens during the spring and summer months when there is reduced rain and warmer weather. The warmer temperatures and dry air helps new seal stick to the road and ensures the durability and quality of the finished product.

This summer’s programme (September 2025 – May 2026)

This season, we are investing in another large road rebuild programme in Northland, along with a large number of resealing and resurfacing sites across the region. This rebuild programme is in addition to our regular maintenance of the network that takes place each summer.

This significant additional investment in the Northland state highway network will mean you see a lot more activity out on the roads, especially during the peak summer. This investment aligns with the Government Policy Statement (GPS) Land Transport by demonstrating improved network condition, preventing further deterioration, reducing costs, and minimising disruptions. The work will be delivered on behalf of NZTA by our contractors.

We’ll make sure to minimise any disruptions to road users as much as we can while we complete these important works, which will improve the road and make everyone’s journey safer and more enjoyable.

  • Current works

    Site / location

    Type of work

    Scheduled dates

    Expected traffic impact

    SH10 Oromahoe 

    Road rebuild 

    Thursday 20 November to Friday 12 December 2025 (drainage works)

    Road rebuild works closure dates:

    • Tuesday 13 January 2026, 7pm to Friday 16 January 2026, 7pm 
    • Monday 19 to Friday 30 January 2026, daily from 7am to 7pm 
    • Contingency: Monday 2 to Wednesday 4 February 2026, daily from 7am to 7pm 

    Drainage works: Stop/go and speed restrictions, day and night

    Road rebuild works: Full road closure with detour

    SH1 Mangamuka

    Road rebuild

    December 2025 – TBC 2026

    Day works – stop/go and speed restrictions

    SH14 Tangowahine (Jacks Point)

    Road rebuild

    January – February 2026 (6 weeks)

    Day works – stop/go and speed restrictions
    24/hr traffic management in place

    SH12 south of Galvin Road, Ruawai

    Road rebuild

    January – February 2026 (5 weeks)

    Day works – stop/go and speed restrictions
    24/hr traffic management in place

    SH10 between Backriver Road and Oparihi Road, Mangōnui

    Road rebuild

    January – February 2026 (5 weeks)

    Day works – stop/go and speed restrictions

    Close Back to top
  • Upcoming works

    Site/location

    Type of work

    Scheduled dates

    Expected traffic impact

    SH1 south of Whangārei – Puwera south

    Road resurfacing

    January 2026 (2 nights)

    Night works – stop/go and speed restrictions

    SH1 Otaika Quarry South – near Rewa Rewa Road

    Road rebuild

    January – February 2026 (2 nights)

    Night works – stop/go and speed restrictions

    SH1 Whangārei central –  near Russell Road

    Road rebuild

    Early-February 2026 (2 nights)

    Night works – stop/go and speed restrictions

    SH1 south of Wellsford township

    Road resurfacing

    Early-February 2026 (2 nights)

    Night works – stop/go and speed restrictions
    Possible local road detour

    SH1 Kaiwaka

    Road rebuild

    Early-February 2026 (3 nights)

    Night works – stop/go and speed restrictions

    SH1 between Wellsford and Dome Valley

    Road resurfacing

    Early-February 2026 (2 nights)

    Night works – stop/go and speed restrictions

    SH1 Awanui Township

    Road resurfacing

    Early-February 2026 (2 nights)

    Night works – stop/go and speed restrictions

    SH10 Mangōnui Bypass

    Road resurfacing

    Early-February 2026 (1 night)

    Night works – stop/go and speed restrictions

    SH1 Whakapara / Puhipuhi (stage 2)

    Road rebuild

    February 2026 (3 weeks)

    Night works – stop/go and speed restrictions

    SH16 Inland Road, Kaukapakapa

    Road rebuild

    February 2026 (2 weeks)

    Night works – stop/go and speed restrictions

    SH12 Kaikohe to Waima

    Road resealing

    February 2026 (2 weeks)

    Day works – stop/go and speed restrictions
    24/hr traffic management in place

    SH12/SH15 Kaikohe Township

    Road resurfacing

    February 2026 (6 nights)

    Night works – stop/go and speed restrictions
    Local road detours – TBC

    SH1/SH10 Pakaraka Intersection

    Road resurfacing

    February 2026 (2 nights)

    Night works – stop/go and speed restrictions

    SH1 south of Whangārei – near Marusumi Road

    Road resurfacing

    February 2026 (2 nights)

    Night works – stop/go and speed restrictions

    SH10 north of Taipa Area School (near Pukewhai Road)

    Road rebuild

    February – March 2026 (6 weeks)

    Day works – stop/go and speed restrictions

    SH10 Zidich Road, Kaingaroa

    Road rebuild

    February – March 2026 (6 weeks)

    Day works – stop/go and speed restrictions

    SH12 Paparoa township

    Road rebuild

    Mid-February – Mid-April 2026 (8 weeks)

    Day works – stop/go and speed restrictions

    SH16 between Stewart Street and Rata Street, Helensville

    Road resurfacing

    Early-March 2026 (3 nights/days)

    TBC

    SH1 Otaika Quarry South – near Quarry Road

    Road rebuild

    March 2026 (6 nights)

    Night works – stop/go and speed restrictions

    SH1 Whangārei central – Cheviot Street to Fourth Avenue

    Road rebuild

    March 2026 (2 nights)

    Night works – stop/go and speed restrictions

    SH12 between Hodgson Road to Wallace Road, Ruawai

    Road rebuild

    March – April 2026 (6 weeks)

    Day works – stop/go and speed restrictions
    24/hr traffic management in place

    Close Back to top
  • Completed works

    Site/location

    Type of work

    Scheduled dates

    Expected traffic impact

    SH12 Oue Hill (between 1414 State Highway 12 and the corner past Wharekawa Road)

    Road rebuild

    Mid-September – late-October 2025 (6 weeks)

    Day works – stop/go and speed restrictions

    SH15 Ruakaka – at Rama Road intersection and Marsden Point Road intersection

    Road resurfacing

    October 2025 (3 nights)

    Night works – stop/go and speed restrictions

    SH12 Mamaranui to Dargaville

    Road resealing

    Mid-October 2025 (3 days)

    Day works – stop/go and speed restrictions
    24/hr traffic management in place

    SH12 south of Dargaville

    Road resealing

    Late-October 2025 (4 days)

    Day works – stop/go and speed restrictions
    24/hr traffic management in place

    SH1 near Wayby Valley Road, south of Wellsford

    Road resurfacing

    November 2025 (2 nights)

    Night works – stop/go and speed restrictions

    SH1 south of Springfield Road, Oakleigh

    Road resealing

    November 2025 (3 weeks)

    Day and night works – stop/go and speed restrictions

    SH12 near Nurse Cavell Lane 

    Road rebuild 

    Late-October – November 2025 (5 weeks)

    Day works – stop/go and speed restrictions 

    SH1 Brynderwyn Hills

    Road resurfacing

    13-16 November 2025 

    24/7 full closure with detours 

    SH1 Towai 

    Road rebuild 

    Mid-July – November 2025 

    Day works – stop/go and speed restrictions 

    SH12 near Blong Road, Ruawai

    Road rebuild

    October – November 2025 (7 weeks)

    Day works – stop/go and speed restrictions
    24/hr traffic management in place

    SH12 near Baylys Coast Road, Dargaville

    Road rebuild

    November – December 2025 (5 weeks)

    Day works – stop/go and speed restrictions
    24/hr traffic management in place

    SH1 Oakleigh 

    Road resealing, and rebuild of the passing lane

    November – December 2025 (2 weeks) 

    Night works – stop/go and speed restrictions 

    SH1 Whangārei central – Central Avenue intersection 

    Road resurfacing 

    November – December 2025 (8 nights) 

    Night works – stop/go and speed restrictions 
    Local road detour for residents via Fifth Avenue 

    SH1 Whangārei central – near Kensington Sports park

    Road rebuild

    December 2025 (6 nights)

    Night works – stop/go and speed restrictions

    SH1 Akerama

    Road rebuild

    Mid-October – December 2025 (8 weeks)

    Day works – Contraflow (lane shift) and speed restrictions

    Close Back to top

Winter programme (May – September)

Winter may bring colder, wetter conditions, but our Northland maintenance teams stay busy keeping state highways safe. While road resealing isn’t suitable in winter, essential work continues, including drain clearing, vegetation control, and pothole repairs. Potholes can occur year-round but are more common in wet weather. Our crews respond to issues as they arise, especially after heavy rain.

Winter can be tough on our roads, and unexpected closures from flooding or slips can occur. Our crews often work in challenging conditions to restore access and make roads safe as quickly as possible. With shorter days, more work happens at night, where lower visibility makes it harder to see road crews—please stay alert and follow traffic signs to help keep everyone safe.

Although major road rebuilds, resurfacing and resealing happens in warmer months, planning for the next season begins well in advance. Throughout winter, our teams assess highways, checking road surfaces, drainage, and 17,000+ assets, including bridges, signs, and streetlights. This helps prioritise summer work where it’s needed most, minimising future disruptions.