CYCLONE GABRIELLE UPDATES: View our traffic map for the latest available information on road closures and delays.(external link)

SCAM ALERTS: Report a phishing scam or learn about the latest phishing emails

TRAFFIC UPDATES: Several roads have been impacted by recent weather events. We’ll provide updates on our Journey Planner website as information becomes available. View our traffic map for road closures and delays(external link)

SCAM ALERTS: Report a phishing scam or learn about the latest phishing emails

CONTACT CENTRE WAIT TIMES: Our Contact Centre is currently experiencing significant wait times. View frequently asked questions

ONLINE TRANSACTIONS: We are experiencing issues with credit and debit card transactions on our website. We are working with the payment provider to resolve this as soon as we can. 

CONTACT CENTRE WAIT TIMES: Our Contact Centre is currently experiencing significant wait times. View frequently asked questions

REGO AND RUC LABEL ERROR: There was a postage error with labels purchased on the 15 August 2022. Find out more

ROAD USER CHARGES (RUC) DISCOUNT: Find out more about the temporary RUC reduction scheme

ONLINE SERVICES: We are currently experiencing issues with all our online services at the moment. We are working to resolve the services as soon as possible. We apologise for any inconvenience caused.

COVID-19 SERVICES UPDATE: Information on Waka Kotahi services, extensions and more

ONLINE SERVICES: We currently have an issue with receiving some payments and are working to resolve this issue as quickly as possible. We apologise for any inconvenience.

EASTER WEEKEND – PLAN AHEAD: Heading away for the long weekend? Check our holiday journeys tool(external link)

SCAM ALERTS: Refund email and Vehicle licence (rego) renewal phishing emails

CONTACT CENTRE PHONE LINES: Our Contact Centre phone lines are currently unavailable. View frequently asked questions

SH2 closure for construction of second Bay Link bridge

|

State Highway 2 will be closed between Bayfair roundabout and Te Maunga intersection during the first weekend of July to enable construction of the second of Bay Link’s three bridges.

Waka Kotahi NZ Transport Agency Regional Manager Infrastructure Delivery Jo Wilton says the closure is critical given the equipment required to install 10 concrete beams – the main structural element of the new SH2 bridge – across the Te Maunga intersection.

“This is a significant closure that will impact people’s weekend travel. A 350-tonne crane is required to install the new bridge beams. Work will take place during day and night shifts to minimise the duration of the closure.”

Located at Te Maunga intersection, the new bridge will span SH2.

For the bridge to be constructed, SH2 between Bayfair roundabout and Te Maunga intersection is anticipated to close from approximately 10pm on Friday 2 July until 5am on Monday 5 July 2021. During the closure, 10 reinforced concrete beams (26m long and weighing 47 tonne) will be placed across SH2 near Te Maunga intersection by a crane positioned in the middle of the state highway.

“As delays are anticipated, we recommend people plan their travel outside of this closure where possible, use alternative routes and allow extra time for travel,” says Ms Wilton.

A signposted detour is available via Girven Road, Maranui Street, Sandhurst Drive and the Sandhurst Drive/Mangatawa Interchange.

Ms Wilton says it’s great to see so much progress on the project.

“Following construction of the bridge spanning the East Coast Main Trunk railway line in February, this is the second bridge to go up in a matter of months.”

The interchange bridge at Te Maunga is anticipated to open next summer under temporary traffic management.

“Once operational, Te Maunga interchange bridge will carry all State Highway 29A traffic to and from the SH2 interchange, removing the need for motorists to cross the railway line and allowing traffic to flow more freely onto the Tauranga Eastern Link. Upon project completion, the finished interchange bridge will transform the intersection and improve safety.”

Following placement of the beams, further work is required to complete the bridge deck and barriers along the edges. After the bridge deck is poured a settlement period will begin, this allows the earth to settle once loads are applied to the ground below. This area will lay dormant until the majority of expected settlement has occurred, a process which is anticipated to take approximately three months.

If this work is impacted by weather or other unforeseen issues, it will be carried out on the next available weekend.

Waka Kotahi thanks motorists, local residents and businesses for their patience during the closure. We would also like to acknowledge Baypark Events Venue and Tauranga Airport for their work to accommodate this closure around major events and airspace considerations.

For more information, visit the ‘State Highway 2 closure’ tab on the Baypark to Bayfair Link project page

Baypark to Bayfair Link project

Map showing where State Highway 2 will be closed between Bayfair roundabout and Te Maunga intersection during the first weekend of July to enable construction of the second of Bay Link’s three bridges