SH1B Telephone Road rail crossing

Section menu

Project introduction

The State Highway 1B Telephone Road rail crossing was closed when the tracks were damaged by a truck in April 2022. The crossing has been upgraded allowing it to safely reopen to traffic on 30 July 2025.

  • Project type

    Road management
  • Project status

    Completed

Background

The rail crossing was closed due to repeated incidents where low vehicles damaged the railway tracks, raising the risk of a derailment for the approximately 38 trains a day which use this line.

The railway line is higher than the road on either side of it and this has caused some longer and lower trucks to scrape and dislodge sections of track as they cross.

NZ Transport Agency Waka Kotahi (NZTA) and KiwiRail made the decision to close the crossing while the future of this intersection was decided.

This rail crossing has been assessed by KiwiRail as being one of the most dangerous of 1300 public rail crossings in New Zealand, using the Australian Level Crossing Assessment Model (ALCAM). 

  • Improvements

    In late 2024, NZTA and KiwiRail agreed on a package of improvements at the rail crossing and nearby Telephone Road/Holland Road intersection that would allow Telephone Road to reopen to through traffic.

    The improvements see the road level raised, new escape lanes built and improved signage and road marking. The road surface haas been raised by up to 410mm over a distance of 90 metres on Telephone Road north of the rail crossing and on Telephone Road/Holland Road/Marshmeadow Road south of the rail crossing.

    Escape lanes built on the north side of Holland Road, either side of Telephone Road, ensure longer vehicles heading south do not stack across the rail line as they wait to turn into Holland Road. For vehicles travelling east on Holland Road and wanting to turn left into Telephone Road, the escape lane provides a safe place to wait if access to Telephone Road is blocked by a train.

    Work began on the improvements in February 2025, and construction was completed in late July 2025.

    More information about the improvements(external link)

    Close